The last day of concrete casting to finishing the second floor.
August 27, 2020
As an act of goodwill, the Southside men were treated with a special lunch today. Chairman of the Foundation Dr. Rene Villanueva and Chairman of the Building sub-committee served the food to the workmen in appreciation of their hard work in completing the second floor on schedule.
Laying of blocks should start next week and work on the ground floor that will be used for parking will also commence next week.
Our block campaign continues…….remember that each block counts and will add up to the 5,000 needed for the building. $5.00 a block, we are counting on the support needed to complete the home of Scouting in Belize.